When does shower glass go in during a bathroom remodel?

Shower glass goes in near the end of a bathroom remodel, after tile, grout and plumbing trim and before the final walkthrough. For Accurate Glass & Mirror, a Bergen County NJ glass shop, the sequence has three handoffs: blocking behind the wall while the studs are open, a free in-home measure once the tile is grouted, and the valve trim and shower head on before the door is hung.

Framing Stage: Blocking Where the Hinges Will Land

Shower glass enters a bathroom remodel long before any glass exists. While the studs are open, solid blocking goes in where the hinges and any clamps will anchor, before the cement board covers it, and how that blocking is used on install day has its own answer. The National Glass Association's frameless shower guidance says a side-mounted hinged door normally requires structural wall construction to carry it, and framing is the one stage when that is simple to provide.

A photo of the open wall, taken with a tape measure run across the studs before the board goes up, is worth more at the glass measure than any drawing, because it shows exactly where the blocking went. The curb, its pitch and the waterproofing belong to the tile contractor, and they only need to be finished and final by the time the glass is measured.

Grout, Then the Measure, Then Fabrication While the Room Finishes

The shower glass measure waits for finished tile, because glass is cut to grouted walls and a capped curb, never to backer board, and the custom glass measuring answer describes how those readings are taken. Once the numbers are in, the glass is cut and edged in the Lodi shop, then tempered, and the hinges and handle are ordered in the chosen finish. That fabrication stretch is when the rest of the bathroom catches up: paint, the vanity, lights and the plumbing trim.

Plumbing trim goes on before the door is hung. The valve handle has to turn freely with the door open and closed, and the angle of the shower head decides where water strikes the glass, so both should be in their final positions when the crew sets the panels and checks the swing. The weeks between measure and install, and what can stretch them, belong to the answer on installation timing.

What the Contractor and the Homeowner Each Hand Over

A contractor hands over a finished opening: tile grouted, curb capped, blocking where it was planned, valve trim on, and a clear path wide enough to carry panels through the house. Working alongside contractors and designers on that schedule is described on the contractor partners page. The homeowner hands over decisions: hinge side, swing, handle position, glass type, and a hardware finish such as polished chrome, brushed nickel, matte black or oil-rubbed bronze.

A change to the opening after the measure means measuring again. A retiled wall, a rebuilt curb or a valve moved over calls for a second measure, and if the panels were already cut to the old numbers, tempered glass cannot be recut to the new ones. Settle the tile, the curb and the plumbing first, and the glass can be the last trade in the room.

Related Questions

People Also Ask

The vanity mirror can be measured at the same visit once its wall is ready. A mirror is cut to a finished wall with the vanity set and the light and outlet positions final, since the glass is cut around them. If any of those are still moving when the shower is measured, the mirror waits for its own visit rather than being cut to a guess.

Painting first is the cleaner order. The National Glass Association says glass must be protected during all stages of construction from debris such as cement, paint, varnish and adhesives, and new glass in a room still being painted has to stay protected the whole time. Paint the walls and ceiling while the panels are being fabricated, then let the glass go in last.

Keep reading

Bring the Glass Into Your Remodel While the Studs Are Open

Call the Lodi shop at (201) 460-1313 while the walls are still open to talk through where the hinges will land, then book the free in-home measure once the tile is grouted. Bring a tile or trim sample to the glass-and-finish selection wall at the Lodi showroom, walk in Monday to Friday 9 to 5 or Saturday 9 to 4.